ARKNRGY / Project tracker / Philippines
FFHC Bagasse-Fired Cogeneration Biomass Power Plant
Biomass, 21.8 MW, Philippines (Talisay City, Negros Occidental), Operating.
- Country
- Philippines, Talisay City, Negros Occidental
- Technology
- Biomass
- Capacity
- 21.8 MW
- Stage
- Operating
- Project company
- First Farmers Holdings Corporation
- Source
- DOE Awarded Biomass Projects as of 31 May 2026, 2026-05-31
- First tracked
- 2026-09-24
- Last updated
- 2026-09-24
DOE service contract stage: Commercial Operation. Installed capacity 21.76 MW. Visayas, Region VI.